The customer requested gas oil pumping to the daily service tanks of the emergency or normal operation power generator units.

Solution adopted by INPRO

The boiler room installation is composed of two main storage tanks, two motorized valves, a twin pressure group, and five modulating inlet ramps for burners including pulse emission MGI gas oil meters. All equipment is controlled by a PLC.

EQUIPMENT

  • Main tank control: EDM-40 probe
  • Leaks detection: DDP-25 interstitial chamber detector
  • Pump system: 1 x duplex fuel pump ATAM-GET (2.100 l/h)
  •            1 x duplex fuel pump GP-800 (800 l/h)
  • Pumpset control cabinets: Inpro CAG+
  • Alarm KIT
  • Solenoid valves: to control the filling process
  • Collector tray with leak detector
  • Level switch: SMMR

Want to know more details about this project?

If you belong to the engineering, construction or project consultancy sector and you want to know more information about this project and many others about hospitals, airports, data centers, shopping centers, etc… you can download our project dossier here.






    Diesel supply for Backup Critical Facilities

    We are specialized in the design and manufacture automatic fuel, pumping systems for critical backup installations, and industrial and commercial heat production.

    We develop engineering bespoke solutions for automatic supply of boilers and power generation plants in:

    • Hospitals
    • Data centers
    • Airports
    • Office buildings
    • Residential buildings
    • Malls

     

    Another projects